Office and administration buildings
Reconversion and change of use of high rise apartments in Ziolkowskistraße 9 to a bank with fewer residential floors
Heating
- heating produced by a biomass boiler
wood pellets (215 kW)
- separate heating circuits for bank, residential
quarters and ventilation
- horizontal distribution
- flat radiators and convectors in the
glass façade area
Sanitary
- higher medium standard sanitary fittings
- central water heating
- pressurisation and fire extinguisher installation
Electrical
- medium standard lighting, installations, fire alarm,
house alarm and video observation installations
- emergency lighting and back up power plant
(100 KvA)
- structured wiring, telephone and BK installations
- electrical operation of exterior blinds
- RWA plant, elevator and lightning conductor |
|
 |
|
 |
| Status |
|
Perspective |
Ventilation
- Extraction and ventilation plants with heat recovery
- decentralised cooling for server rooms
- decentralised extraction for the toilet rooms
- mechanical smoke extraction |
| Contractor: |
DKB |
| Planning: |
BBP Bauconsulting |
| Period: |
2001 |
|