  E.-Bennert-Straße 12-29
Schwerin-Lankow
New construction of car park

Contractor: WGS

Architect: Dipl.-Arch. A. Köppen

Planning: 1995/1996
Completion: 1997/1998
Planning services: architecture, building physics,
stress analysis, soundproofing
and utilities
Building costs: 2,100,000 DM
92 parking spaces

 

Measures:

Construction of a car park on a 9,600 m2 building lot with 92 double parking spaces with natural ventilation, deaeration and compliance with the soundproofing requirements for the adjacent residences
- area built on: 1,138 m2
- net area: 1,0996 m2
- entry and exit over a ramp
- circulation by direction oriented traffic lane